Cllr. Rob Power spoke on Monday morning's Kildare Today.
Cllr. Rob Power estimates that the Caragh Bridge will be under construction for another two weeks.
The scafolding went up on Friday, because the bridge is a protected structure, scafolding cannot be attached to the bridge, said Cllr.Power.
A conservation architect is working on the bridge, he is waiting to see a trial wall, and then give the go ahead on the bridge.
Cllr. Power said the Thomastown road will now need repair because of the increased traffic.
"HGV's have been pushed down this route," he said.
Engineers have been looking at the road and will consider any patchwork, he added.
Fianna Fail Cllr. Rob Power spoke to Eoin Beatty on Monday morning's Kildare Today:

Burglary Rates Fall Across Kildare-Carlow Despite National Rise
Driving Test Centre For Leixlip & Celbridge Area Moves A Step Closer
Kfm Obituary Notices
Councillor Believes Bollards In Naas Are Causing Issues For Patrol Cars Pursuing Drug Dealers
Gardaí Appeal After Window Of County Council Office Smashed
Council Asked To Engage With EPA Amid Odour Emissions At Facility In Kill
Kildare Agri Business Funded €5M For Biomethane Strategy Set To Begin Project Today
Progress Made For Provision Of Kildare's First Designated Bathing Area