Costs have now passed a billion euro with 18 months still to go until completion.
The state is open to a further risk of an overspend at the National Children's Hospital, that's according to the chairman of the Oireachtas Public Accounts Committee.
The committee has been told almost three quarters of the Budget has already been spent, which has now surpassed €1 billion.
In 2015 the new Children's Hospital was estimated to cost 650 million euro and promised to be built by 2020.
Costs have now passed a billion euro with the majority of building works not due to be complete until January 2024, with the hospital to open a year later.
A new budget of 1.4 billion euro has been set, meaning almost two thirds of that has been spent with 18 months to go on the build.
Public Accounts Committee Chairman, Brian Stanley, believes there is further financial danger to the state:

Exclusive: Cllr Bill Clear To Join Independent Ireland After Months Of Discussions
WATCH: Car Linked To Attempted Naas Robbery Spotted In Newcastle - Gardaí Warn Public Not To Approach
Court Hears Gardaí Medically Advised Not To Speak To Alleged 10-Year-Old Victim Of Sexual Assault At Citywest
A New Report Has Highlighted Persistent Gaps In Access To Beds In Stroke Units
Department Of Housing Shifts Blame On To Council As Kildare Families Priced Out Of "Affordable" Housing Again
Outbreak Of Bird Flu Has Been Confirmed In Carlow Turkey Flock
Lidl To Open Country’s First Net Zero Energy Store In Maynooth This Thursday
Contract For Maynooth Eastern Ring Road Project Awarded To Company Based In Kilcullen